Update October 22, 2025
All cutting and placement of micro duct is complete, working on pulling terminals and cable in micro duct in green highlighted areas. Dayna Cv will be cut and duct placed. This will completed by next week.
Update September 9, 2025
Green indicates what is complete, and red still has to have trenching done.
Update March 18, 2025